project manager is implementing the quality management plan for a project. The projectmanager has been tracking quality issues that have emerged during the rollout and wants todevelop a strategy for preventing these issues from happening again. Which of the following toolsand techniques can the project manager use? (Select TWO).A. Root cause analysis
Pareto chart