Question of the day

You are responsible for the Program Management role on a project. The project is currently in the Planning Phase. An internal team of developers perform the Development function. An external company is contracted to perform the Test function. Testing requirements are described in the functional specification. The external company creates the test plan. At the same time, the internal team of developers creates the development plan. Both teams submit their plans to you for review. You discover that the members of the internal team did not communicate with the creators of the test plan. The activities specified in the test plan and the development plan seem to be in conflict. You estimate that there is an increased risk that the solution will not be tested adequately. You need to reduce the risk. What should you do?

Answer(s)

  1. Finalize the creation of the development plan. Instruct the external company to create a testplan that is based on the development plan.
  2. Instruct the internal team to create both the development plan and the test plan. Give the finaldevelopment plan and test plan to the external company.
  3. Instruct the two teams to communicate about their plans, and then create revised versions ofthe development plan and the test plan.
  4. Create the master project plan. Instruct the internal team to create the development plan.Instruct the external company to create a test plan that is based on the master project plan.
Correct Answer

Instruct the two teams to communicate about their plans, and then create revised versions ofthe development plan and the test plan.