You are the administrator for Microsoft Office Project Server 2003 for Company.com. Company.com installs Project Server and Microsoft Office Project Web Access. Actual values for vacation time are not displayed when project managers review work in Project Web Access. Project managers need to review actual time values for the vacation time of team members. You must ensure that project managers can review actual values for the vacation time of team members in Project Web Access. What should you do?
Answer(s)
Create a Vacation task. Save the project as an Administrative Project on the project server.