Refer to the exhibit.
Answer(s)
customer has deployed two Cisco MDS 9509 Multilayer Directors. One MDS 9509 is deployedin each of two separate data centers. The primary data center is always active, and thesecondary data center is considered a standby site. The data centers are connected together byan unreliable Gigabit Ethernet connection that is shared by many departments. A replicationapplication is using Fibre Channel over IP (FCIP) as its transport mechanism over the GigabitEthernet circuit. The administrator is concerned about network stability in the production fabricand the impact of a Gigabit Ethernet circuit outage on the production fabric. The administrator isdeploying Inter-VSAN Routing to isolate the production fabric from the standby data center fabric,and only has one license.Where should the administrator install and configure Inter-VSAN Routing?A. Switch A