You are implementing the Drop Ship process flow for Vision Corporation. Consider the following list of steps: 1. Enter Sales Order header and lines. 2. Book Sales Order. 3. Run Order Import concurrent program. 4. Run Workflow Background Process. 5. AutoCreate to create a Purchase order. 6. Run Requisition Import concurrent process. 7. Approve Purchase order. 8. Perform Pick Release Process. 9. Receive against the Purchase order. 10.Perform the Ship Confirm process. Which steps are required, and in which order must they be performed?
Answer(s)
1,2,4,6,5,7,9