- customer plans to install a 4 drawer Power 570 into an existing IBM rack which contains aPower 520, two FC #0595 expansion units and a TS3200 tape library. Which of the followingmust be considered during solution design and installation?A. The 570 MMA CECs must be installed in the bottom of the rack
- Intelligent PDUs are required in the rack to support this configuration
- Contiguous rack space must be allowed for the 570 due to inter-CEC connectors.
- The earthquake feature is required on the rack to provide support for the mechanical load.
Correct Answer
Contiguous rack space must be allowed for the 570 due to inter-CEC connectors.